The government has terminated 38 road and bridge contracts classified as non-performing under the Department of Roads. More termination notices are expected soon, according to department data. Contracts were canceled for failing to meet deadlines despite repeated extensions, violating basic contract terms, or being abandoned by contractors. The largest project scrapped so far is the Kankai Bridge in Jhapa, which reached just 65 percent completion after 14 years and five deadline extensions.